Suki Kinari Hydropower Station, Naran,Khyber Pukhtunkhwa

Land acquisition award announced on 17th Nov, 2016
Three Gorges Second And Third Wind Power Project

Financial Close March 2017.
Sachal Wind Farm (Jhimpir, Thatta)

Commercial Operation Date (COD) attained 11 April, 2017
UEP Wind Farm (Jhimpir, Thatta)

Commercial Operation Date (COD) : 16th June, 2017
Hydro China Dawood Wind Farm(Gharo, Thatta)
Commercial Operation Date (COD) attained 5th April, 2017
Quaid-E-Azam 1000MW Solar Park (Bahawalpur) Quaid-E-Azam

COD of 4x 100 MW attained in August 2016
Surface Mine In Block II Of Thar Coal Field, 3.8 Million Tons/Year

Financial close attained in April 2016
Engro 2x330MW Thar Coal Power Project
Financial Closed (FC) achieved in April, 2016.
HUBCO Coal Power Project, Hub Balochistan

Ground breaking ceremony held on 21 March 2017
2×660MW Coal-Fired Power Plants At Port Qasim Karachi

Ist Unit Inagurated in November 2017